In Engineering / College | 2025-07-03

A project is designed to refurbish the class rooms of B Sc yr 3 of Milton Margai Technical University Congo Cross Campus for 2024/2025 academic year with the following activities and precedence relationship.

Activities Predecessor Duration (Days)
A - 3
B - 5
C B 2
D A 1
E A 3
F D 6
G D,C 3

Required:
a. Construct a NETWORK DIAGRAM to represent the above project activities on a noddle
b. Construct a GANTT CHART which will provide an overview of the planned project
c. Determine he Shores time necessary to complete the project
d. Which activities needs to be completed on time in order to ensure that the project is completed as soon as possible

Question 2.
a. What is a problem? MMTU Congo Cross Campus is faced with acute sanitation problem; design a sanitation project to address this problem.
b. Develop a logframe for this sanitation project with at least two (2) objectives

Asked by isaacmarrah3

Answer (2)

The project focuses on refurbishing classrooms through a structured plan involving a network diagram and a Gantt chart to outline activities and timelines. The shortest project completion time is determined to be 13 days, identifying critical activities needed for timely completion. Additionally, a sanitation project logframe addresses sanitation issues at MMTU with defined objectives for facility access and hygiene awareness.
;

Answered by Anonymous | 2025-07-03

The answer provides a structured approach to refurbishing classrooms with a network diagram, Gantt chart, and critical path analysis. It also addresses the sanitation issue at MMTU by proposing a sanitation project with a logframe and objectives. Understanding task relationships and project planning is crucial for project success. ;

Answered by GinnyAnswer | 2025-07-03